Use this article when you want to complete the ECR Governance Spreadsheet for the IP/Legal Review process
Step-by-step guide
- Download the ECR Governance Spreadsheet Template to your laptop.
- Rename the file by replacing 'Template' with your project name.
- Open the ECR Governance Spreadsheet
- Enter your answers in column C (Answers) for the following:
- CORE-001 through CORE-007
- IP-001 through IP-004-h
- Add comments in column D (Comments) for any rows where additional information is required.
- Enter your answers in column C (Answers) for the following:
If you answered YES to any of the rows between IP-004 d-h, you must complete the remainder of the spreadsheet (IP-005 through IP-009)
If you do not complete ECR Governance Spreadsheet for the IP/Legal Review, your code will not be shared until the legal opinion has been rendered.
- Once the ECR Governance Spreadsheet has been completed, upload it to the Submit Reusable Code request you opened on the SDO Service Center.
What happens next?
- The SDO Service Center team will forward the completed spreadsheet to IP/Legal Review for an official opinion.
- IP Legal will either approve or decline the reuse of the code, with justification
- The SDO Service Center team will notify you via the SDO Service Desk request.
- If approved (or approved with restrictions),
- SDO Administrators will reset the permissions on the project.
- Project Administrators will configure the document repository so their code becomes searchable.
- Project Administrator will set the user permissions on the repositories as desired.
- Users can begin browsing the code.
- If denied
- the project will be deleted